1.0 SCOPE
This method statement describes the work procedures, quality
assurance, and quality control for the concrete blinding at sub-structures.
2.0 RESPONSIBILITY
The Project Manager is overall responsible for all aspects
of the works/project.
The Project Site Engineers are responsible for the proper
execution, arrangement, coordination, and supervision of the quality, safety,
and delivery of work.
The QA/QC Manager/Engineer shall ensure that the execution
team follows this method statement and implements the site inspection
procedures.
The MEP Coordinator/Engineers are responsible for
coordinating the Mechanical and Electrical works related to underground works.
The Safety Engineer will ensure the implementation of safety
on the worksite.
The Approved Ready Mix Concrete Supplier is responsible for
the continuous delivery of concrete as per the approved design mix and project
specifications, from batching and transporting to controlling the temperature
and slump tests, as well as taking the required concrete test cube samples upon
arrival on-site.
3.0 MATERIALS & EQUIPMENT
Blinding Concrete: Ready-Mixed, as per the approved
design mix by Engineers/Consultants.
Mobile Concrete Pump
Mobile Tower Crane (If required)
Bonding Agent (if required)
Approved Gauge Polyethylene Sheets
Clean/ Potable Water
Power-Driven Floats
Wooden/ Aluminum Screeder Bar
Dumpy Level with Stadia Rod
Air Compressor
4.0 WORK PROCEDURES
Preparation Works
Excavation works up to the formation level of the
sub-structures should be completed and checked for required elevations by
Engineers and the approved Independent Testing Agency to ensure bearing
stability.
For normal excavation of undisturbed earth, the cut earth
surface at the formation level should follow the standard method statement for
soil backfilling.
Establish the reference 1.0m elevation from SSL and the
high-level elevation of the concrete surface for blinding, with a minimum
requirement of 75mm. Shuttering should be provided around the perimeter ends of
the proposed casting area.
Approved soil treatment/anti-termite must be applied prior
to laying polyethylene sheets on the soil surface.
Install the approved polyethylene sheet on top of the soil
surface, as per the installation procedure by the manufacturer or supplier.
Concreting Works
Blinding concrete shall be poured on the prepared area using
a concrete pump for large volumes, or direct pouring with a chute, following
the basic method statement for placing concrete using a mobile pump or direct
pouring.
In case of delays in the concrete, the incomplete poured
strip should be treated with bonding agent and/or cement slurry before placing
fresh concrete.
When the ready-mix concrete is placed or poured on the area,
level the concrete according to the approved blinding level.
The surface finish of the blinding shall be smooth, using
power-driven floats to achieve the required surface finish for receiving
waterproofing membranes.
Curing & Protection
During concreting and throughout the initial hardening, the
blinding shall be immediately cured with an approved curing compound or water
curing.
The work area shall be closed off from traffic during
preparation, concreting, and curing.
Slump Test & Temperature Control
Slump tests and temperature checks of the concrete will be
carried out for every truck mixer that arrives on-site. Results will be
recorded in the delivery ticket and the concrete monitoring log prior to
placement at the site. The slump test and temperature will follow the approved
design by Engineers.
Concrete Test Cubes Sampling
The frequency of sampling concrete cubes shall be as per the
instructions of the Engineers/Consultants or according to standard
specifications. Concrete sampling shall be carried out in accordance with
Clause of BS 1881 Part 102.
5.0 FIELD QUALITY CONTROL & INSPECTIONS
The necessary site inspections, as stated in the work
procedures, shall be carried out in accordance with the site inspection
procedures.
Site Engineers and Project Engineers will monitor the
execution of work to ensure compliance with this method statement.
Upon completion, a joint quality inspection between the
Contractor, QC Engineer/Project Engineer, and the Consultant’s Engineer shall
be carried out to verify the quality of the finished surface of the blinding.
Any unsatisfactory workmanship or defects found shall be rectified, and
preventive actions shall be taken to avoid recurrence in subsequent works.
6.0 SAFETY PRECAUTIONS
Prime importance shall be given to the safety of personnel
and protection of utility services. Ensure that personnel involved are
thoroughly aware of the company’s safety regulations.
Any machinery and equipment must only be operated by
well-trained and experienced personnel.
Protective clothing and equipment will be necessary. Ensure
that any special clothing or equipment required (including signs relating to
the wearing of rubber boots, helmets, eye protection, ear defenders, visibility
vests, etc.) is ordered and available for use on-site. Ensure that
subcontractors are made aware of any site requirements, especially regarding
the wearing of safety helmets. Instruct staff in the correct handling and
lifting of materials, especially those that could cause injury to the hands.
A risk assessment letter should be issued by the Safety
In-charge before the start of the activity, and it should be posted immediately
at the working area during the activity.
7.0 REFERENCE DOCUMENTS
Project contract specifications
Project contract and Approved Shop Drawings
No comments:
Post a Comment