Check that the latest approved as-built / Shop Drawing is
attached.
Check that the material used in the installation is in
accordance with the approved material technical submittal.
Check that the conduit route is as indicated on the latest
approved construction drawing.
Check that the conduit system is installed according to the
type of circuit category.
Check that the installation permits easy drawing of cables.
Check the alignment and rigidity of the conduit
installation.
Check that the conduits and fittings are of the size and
type indicated in the drawings and are manufactured in accordance with
specification requirements.
Check that all field bends are free of cuts, dents, or
flats.
Check that the cut ends of the conduit are reamed to remove
rough edges.
Check that all joints between lengths of conduit, and
between conduit couplings, fittings, and boxes, are made using approved
methods.
Check that the conduit supports are spaced 1.0 meter apart
for straight runs and within 200 mm on either side of bends or boxes.
Check for a minimum of 25 mm of concrete covering above the
conduit to avoid cracks in the slab.
Check that the number of bends in a run of conduit between
pull points does not exceed the equivalent of two quarter bends (180 degrees
total), including bends located immediately at the boxes.
Check that the boxes are properly oriented for the
installation of wiring accessories.
Check the installation of expansion couplers as per site
requirements.