METHOD STATEMENT FOR APPLICATION OF LIQUID BITUMINOUS DAMP PROOFING AT SUB-STRUCTURE

 1.0       SCOPE

The intension of this method statement is to describe the procedure and responsibilities of its person which are application of liquid bituminous dam proofing on sub-structure.

 

2.0              RESPONSIBILITY

2.1              Project Manager is overall responsible for all aspects of the works / project.

 

2.2              The Project Site Engineers are responsible for proper execution, arrangement, co-ordination & supervision for the quality, safety & delivery of work.

 

2.3              Anti-termite subcontractor is the responsible to ensure the delivered chemical are as per approved materials and it is responsible for proper mixing and application at site.

 

2.4              The QA/QC Manager & Engineers shall ensure that execution team is following this method statement & implementing the site inspection procedures. The QA/QC Engineers shall monitor, check, control & document the quality of concrete delivered to site, & the quality of  work during the entire duration of casting.

 

2.5              Safety Engineer or Safety Officer will ensure the implementation of safety at work site.

 

3.0              MATERIALS & EQUIPMENT 

3.1              Approved Bituminous Damp proofing Materials.

3.2              Roller paint

3.3              Recommended Polyethylene 1000 gauge thick.

3.4              Compressor in required

3.5              Broom or brush

 

4.0              EXECUTION 

4.1              Substrate or concrete blinding should be examine with applicator present and Engineers, for compliance with all requirements surface smoothness and other condition affecting of work.

  

5.0              PREPARATION

5.1              Surface preparation of blinding, fill voids, seal joints, cracks and apply bond breakers if required, as recommended by system Manufacture. 

5.2              Mask or otherwise protect adjoining exposed surfaces from being stained, spotted or coated with water proofing materials. Prevent water proofing materials from entering and clogging weep holes and drains.

5.3              Applicator of Liquid Damp proof shall be approved or certified by manufactures

 

6.0              application

6.1              Application, General

Comply with Manufacture written recommendation unless more stringent requirements are indicated or required  by protect conditions to ensure satisfactory performance the system

6.1.1        Apply additional coat if recommend by manufacture or required to achieve coverage indicated.

6.1.2        Apply second coat at right angle direction to first coat.

6.1.3        Allow each coat of waterproofing to cure, before applying subsequent coats.

6.2       Application for Sub-structure.            

6.2.1    Ensure that concrete surface is clean, smooth and dry.

6.2.2    Ensure that prior to application of waterproofing all services penetration are completely in place and inspected by Engineers.

6.2.3    Apply the liquid Damp proof materials continuously on the blinding surface  area with one Layer and let dry or cure in as per manufacture recommendation prior to continue the subsequent layer. 

6.2.4    Application or termination on MEP embedment shall be as per approved detail drawing which is recommended by sub-contractor.

6.2.5    When application of damp proof is finish, engineers should be inspected and approved the application prior to installation of approved polyethelyne sheet.

6.2.6    Support protection course with spot application of trowel-grade mastic.

 

7.0              FIELD QUALITY CONTROL 

7.1              Monitor the materials delivery and application of materials.

7.2              Application of Damp proof should inspect and approved by Engineers prior screed.

 

8.0              SAFETY PRECAUTION

8.1              Prime importance shall be given to safety of personnel and protection utility Service. It ensures that the personnel involved are thoroughly aware of the company Safety regulation.

8.2              Any Machineries and Equipment must operate only by well trained and experienced personnel.

8.3              Protective clothing and equipment will be necessary and will ensure that any special protective clothing or equipment required and any signs relating to the wearing of helmets, eye protection, ear defenders, visibility vest etc., are ordered and available for use on site and that subcontractors are made aware of any site requirements, especially for the wearing of safety helmets.

8.4              Instruct staff in the correct application of hazard chemicals which could cause injuries to the hands.

8.5              Risk assessment letter should issue by Safety In-charge before start of activity and immediately post at the working area during activity.

  

9.0          Reference Documents

  9.1   Project contract specifications

       9.2   Project contract drawings general Notes   