GROUTING -QUALITY CONTROL CHECKLIST

Check that the area is ready to receive the grouting.

Ensure that the structural column erection is complete, checked for alignment, plumb, and elevation, and accepted for grouting.

Check that the concrete foundation top is cleaned of dirt, laitance, oil, and grease.

Ensure that the anchor bolt boxes and sleeves are cleaned of all polystyrene and other deleterious materials.

Ensure that the grouting material used is approved by the consultant/client.

Check that the grouting material is mixed according to the manufacturer’s instructions and by mechanical means.

Ensure that the surface of the concrete is thoroughly wetted and that no excess water remains on the surface or in the pockets prior to grouting.

Ensure that the grouting is placed first in anchor bolt boxes/sleeves and then below the base plate, as per the manufacturer’s instructions.

Check that the grouting is done as per the specifications and drawing.

Ensure that curing is done on the exposed surface as per the manufacturer’s instructions.

 