Check that the block work check sheet is signed.
Verify that the mock-up area is approved by the
consultant/client.
Ensure that all concrete surfaces are properly scabbled
prior to plastering.
Ensure that embedded services are tested, if necessary,
prior to plastering works.
Verify spot levels with mortar to maintain uniform plaster
thickness before proceeding with plastering.
Ensure that all door sub-frames are fixed prior to
plastering.
Verify that the plaster material and mix are approved.
Check that the mix is done using a mechanical device.
Ensure that all corners are angular and equal.
Check that all plastering accessories are installed as per
the drawing and specifications.
Ensure that the application, thickness, and number of coats
of plaster are as per the specifications and drawing.
Ensure that the control joints are as per the specifications
and drawing (wall area not more than 13 sq. meters).
Check that the surface finish is accepted and within
tolerance (3 mm in a 3-meter straight edge in any direction).
Ensure that spilled mortar is removed from the site and the
area is kept tidy.
Check that moist curing is done as per the specifications
and that the plaster is acceptable.