SCOPE
The intention of this method statement is to describe the procedure and
responsibilities of personnel involved in the application of anti-termite
treatment on the sub-base of the structure.
2.0 RESPONSIBILITY
The Project Manager is overall responsible for all aspects
of the work/project.
The Project Site Engineers are responsible for the proper
execution, arrangement, coordination, and supervision of quality, safety, and
delivery of work.
The Anti-termite subcontractor is responsible for ensuring
that the delivered chemicals are as per the approved materials. They are also
responsible for the proper mixing and application of the chemicals on site.
The QA/QC Manager & Engineers shall ensure that the
execution team follows this method statement and implements the site inspection
procedures. The QA/QC Engineers shall monitor, check, control, and document the
quality of work during the entire duration of the treatment.
The Safety Engineer or Safety Officer will ensure the implementation of safety measures at the worksite.
3.0 MATERIALS & EQUIPMENT
Approved Anti-termite Materials
Clean Water and Water Pumps
Polyethylene Sheets and Water Drums
Mixing Equipment (if necessary)
4.0 EXECUTION
The soil substrate should be approved by engineers and the
invert elevation should match the shop drawings.
All materials/chemicals should be inspected and approved by
engineers.
The Anti-termite applicator should be approved or certified by local authorities.
5.0 PREPARATION
The soil surface should be properly compacted (if
necessary), and all loose materials should be removed.
The work should be coordinated with the Safety Department
before proceeding with the activity.
Mixing of materials should be done as per the applicator/manufacturer’s recommendation.
6.0 APPLICATION
Internal Area
Footings – The excavated area of footings will be
treated by spraying termiticidal solution on the exposed soil surface prior to
concreting.
Foundation Walls – The adjacent soil surface along
the perimeter of foundation walls and both sides of interior partition walls
will be treated by spraying termiticidal solution as necessary.
Slab – The soil surface adjacent to building slabs
and attached slabs will be treated by spraying termiticidal solution prior to
concreting.
Penetrations and Joints – Expansion joints, control
joints, and areas where slabs will be penetrated (e.g., around plumbing pipes,
electrical/telephone conduits) will be treated by spraying termiticidal
solution on the soil surface as necessary.
Ground Floor – The ground floor level will be treated
after compaction by spraying termiticidal solution on the soil surface prior to
the floor slab concrete works.
External Area
The soil around the building at the foundation/perimeter
level will be treated as per the manufacturer's recommendation before fixing
the interlock tiles or concrete works.
Special Note: Any structural changes in treated areas
disturbed by construction activities, such as breaking concrete slabs, digging
trenches or pits, re-filling, or leveling, should be reported to the applicator
contractor for re-treatment to restore the chemical barrier.
If the treated area is exposed to ultraviolet rays or heat for more than 24 hours in summer and 48 hours in winter, and is not protected by polyethylene sheets due to delays in concreting works, it is advised to re-treat before proceeding with concreting.
7.0 FIELD QUALITY CONTROL
Monitor the delivery of materials, temperature, mixing at
site, and application.
The application of anti-termite treatment should be inspected and approved by
engineers.
8.0 SAFETY PRECAUTIONS
The prime importance shall be given to the safety of
personnel and the protection of utility services. Personnel involved should be
thoroughly aware of the company’s safety regulations.
Any machinery and equipment must be operated only by
well-trained and experienced personnel.
Protective clothing and equipment will be necessary. Ensure
that any special protective clothing or equipment required (such as helmets,
eye protection, ear defenders, visibility vests, etc.) is ordered and available
for use on-site. Subcontractors should also be made aware of any site-specific
requirements.
Instruct staff on the correct application of hazardous
chemicals that could cause injuries to the hands.
A risk assessment letter should be issued by the Safety In-charge before the start of the activity and should be posted at the working area during the activity.
9.0 REFERENCE DOCUMENTS
Project contract specifications
Project contract drawings and general notes
Nice Blog! Are you searching for termite treatment services in Zirakpur? We provide the best protection to the house and commercial properties from termite. We uses different methods & eco friendly chemical for termite treatment services. Get the termite treemnt services at a reasonable price. Our team provides 100% parmanent solution and 24*7 available for our customers.
ReplyDelete